On the morning of February 23, 2024, CC1 and members of the Mitsubishi-Hyundai-CC1 Contractor Joint Venture cooperated with Vietnam Electricity Group and Power Project Management Board 2 to organize a program summarizing the project emulation movement. Quang Trach I Thermal Power Plant project - 2023 and launched emulation of Quang Trach I Thermal Power Plant project, Quang Trach Power Center Infrastructure project - 2024 in Quang Trach district, Quang Binh province.
Attending the program, from the leaders of Quang Binh province were Mr. Tran Hai Chau - Permanent Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council; Mr. Doan Ngoc Lam - Vice Chairman of the Provincial People's Committee and leaders of relevant departments, branches, branches and localities. On EVN's side, there was Mr. Nguyen Anh Tuan - General Director of EVN; Mr. Nguyen Duc Cuong - Member of EVN's Board of Directors; Mr. Nguyen Tai Anh - Deputy General Director of EVN along with leaders of specialized departments and leaders of Power Project Management Board 2. On the Vietnam Electricity Union's side, there was Mr. Do Duc Hung - Chairman of Vietnam Electricity Trade Union. Male; Mr. Uong Quang Huy - Vice Chairman of Vietnam Electricity Trade Union.
The contractor partnership includes: Construction Corporation No. 1 - Mitsubishi Corporation - Hyundai Design and Construction Company (CC1 - MISUBISHI - HYUNDAI); Joint venture contractor Phu Xuan Construction and Consulting Joint Stock Company - Pacific Group - Water Works Construction Consulting Joint Stock Company (PHUXUAN-PACIFIC-WACOSE); Joint venture of Quang Trung Industrial Group Joint Stock Company - CS Wind Vietnam Company Limited (QUANG TRUNG - CS WIND VIETNAM).
In 2023, CC1, together with the consortium of contractors and consulting units, has made efforts to overcome difficulties and successfully complete the progress milestones committed at the 2023 emulation launching ceremony. Specifically, exceeding the target. Construction progress of foundation items: turbine (3 months ahead of schedule); chimney (3 months ahead of schedule); central control house (1 month ahead of schedule); Besides, the construction of the foundation of the boiler items, water and wastewater treatment systems... all met the competition goal when completed on schedule.
In particular, the project does not allow environmental incidents or occupational accidents to occur. Up to now, the project has achieved more than 4 million safe working hours...
Speaking at the ceremony, Permanent Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council - Mr. Tran Hai Chau emphasized that the projects at Quang Trach Electricity Center are key projects, with important significance in promoting the development of Quang Trach Power Center. To promote and create a breakthrough for the socio-economic development of Quang Binh province, Mr. Tran Hai Chau affirmed that Quang Binh province is committed to continuing to create the best conditions for investors and contractor partnerships to deploy. , striving to complete the project in 2026.
Also within the framework of the program, EVN General Director Nguyen Anh Tuan thanked the Provincial Party Committee, People's Committee of Quang Binh province, departments, branches, branches, and local authorities in Quang Binh province; jointly praised all officers, employees - workers of CC1 and the contractor consortium participating in the project for the achievements achieved in 2023.
With the emulation movement in 2024, EVN General Director Nguyen Anh Tuan called on CC1, the consortium of contractors and consulting units, mass organizations and all employees to unite, respond and implement the movement well. creative labor emulation movement to achieve many high achievements. “With consensus and efforts in the management and administration of construction on the construction site, the support of local authorities, and promoting achievements achieved in 2023, the emulation movement will surely be completed. The goals of construction and installation of Quang Trach I Thermal Power Plant in 2024 will be successful", EVN General Director believes.
It is known that the Quang Trach I Thermal Power Plant project with supercritical technology plays an important role in meeting domestic electricity needs, especially in the Central and Southern regions of Vietnam. Despite facing challenges, CC1 and the contractor consortium always actively work with the investor and related units to closely coordinate and support each other. Through this emulation movement, CC1 and the contractor consortium set a goal of reaching 61% construction progress by 2024, including pre-commissioning of the water treatment system, thereby setting goals and timelines. Clear deadlines for the near future. As a premise to continue promoting the completion of the entire project and putting commercial power generation into operation in 2026, contributing to the economic development of Quang Binh province and ensuring supply to the national 500Kv power grid.