CC1 NEWS

  • Home
  • CC1 PARTICIPATES IN THE 120 DAYS AND NIGHTS COMPETITION LAUNCHING PROGRAM TO COMPLETE THE STEEL STRUCTURE OF PASSENGER TERMINAL T3 – TAN SON NHAT INTERNATIONAL AIRPORT

CC1 PARTICIPATES IN THE 120 DAYS AND NIGHTS COMPETITION LAUNCHING PROGRAM TO COMPLETE THE STEEL STRUCTURE OF PASSENGER TERMINAL T3 – TAN SON NHAT INTERNATIONAL AIRPORT


On the afternoon of May 6, 2024, at the construction site of the T3 Passenger Terminal Project - Tan Son Nhat International Airport, CC1 and the Contractor Consortium participated in the emulation preliminary ceremony to celebrate the 49th anniversary of complete liberation. money in the South, unifying the country - Launching the second round of emulation with 120 days and nights to complete the project's reinforced concrete structure, celebrating the 79th National Day of the Socialist Republic of Vietnam (September 2 /1945 – September 2, 2024)

Attending the program, on the side of Vietnam Airports Corporation (ACV), there was the presence of Mr. Vu The Phiet - General Director. On the contractor's side, there was the presence of Mr. Dinh Van Hung - Deputy General Director of Construction Corporation No. 1 - JSC; Mr. Nguyen Do Quy - General Director of Hanoi Construction Corporation; Mr. Nguyen Thanh Tam - CEO of Ricons Construction Investment Joint Stock Company; Mr. Dang Van Thinh - Deputy General Director of Corporation 319 (Ministry of National Defense); Mr. Le Ngoc An Son - Director of Luu Nguyen Company Limited; Mr. Vo Thanh Phong - Director of Truong Son 3 Board of Management; Mr. Nguyen Le Anh Tuan - General Director of ATAD and representatives of the supervision consulting unit and related guests.

Mr. Dinh Van Hung - Deputy General Director of Construction Corporation No. 1 - Joint Stock Company at the program

Summarizing the first round of emulation activities "90 days to complete reinforced concrete structures at terminal T3", Mr. Vu The Phiet - General Director of ACV said, the items that CC1 and the Contractor Consortium had committed to in advance. That goal has now been accomplished.

CC1 and representatives of the Contractor Consortium received certificates of merit from the Investor

Accordingly, in the first emulation launch from February 2024 until now, CC1 and the Contractor Consortium have shortened the progress from 3-16 days. Currently, CC1 and the Contractor Consortium are speeding up the construction and installation of mechanical and electrical systems, completing the architecture of the 1st and 2nd floors. On the construction site, cranes from 100-300 tons have begun to be installed and restored. Material transfer service for steel structure construction. For the high-rise garage category, the construction progress is transitioning to completing the two-basement architecture. The bridge leading to the terminal and the expanded aircraft apron also achieved more than 80% in volume compared to the target progress.

 In order to shorten the progress, ACV and the contractors continued to sign a contract to launch the second round of competition with "120 days and nights determined to complete the steel structure of the main roof of the station and the high-rise parking garage" on the occasion of the National Day. 9/2.

Specifically, the entire steel structure of the station will shorten the schedule by 69 days, the steel structure of the garage roof will shorten the schedule by 59 days. In addition, the escalator equipment at the passenger terminal will be shortened by 67 days. Luggage conveyor equipment on the second floor of the passenger terminal will be shortened by 44 days.

CC1 and representatives of the Contractor Consortium signed the 2nd emulation contract - Celebrating the 79th anniversary of the National Day of the Socialist Republic of Vietnam (September 2, 1945 - September 2, 2024)

It is known that although the target progress has been shortened, there is still a lot of remaining construction volume. Therefore, each contractor in the Joint Venture needs to make more efforts, focusing financial and human resources to ensure the overall progress of the T3 terminal project, meeting the requirements of the investor.

The bidding package for construction and installation of passenger terminal equipment at T3 will start at the end of August 2023, with a winning value of more than 9,000 billion VND by a consortium including CC1 and 5 contractors: Construction Joint Stock Corporation. Hanoi (Hancorp); Corporation 319 (Ministry of National Defense); Truong Son Construction Corporation; Ricons Construction Investment Joint Stock Company and Luu Nguyen Construction Company Limited are in charge.

Over the past 45 years, CC1 has been known as one of the leading investment and construction enterprises in Vietnam in the fields of industrial, energy, civil, transportation and technical infrastructure projects. With unremitting efforts, CC1 has engraved its name on thousands of projects spread across the country. Recently, CC1 has participated in many key national projects such as: Passenger Terminal - Long Thanh International Airport, Na Duong II Thermal Power Plant, Dai Ngai Bridge Construction Investment Project on Highway 60 of the territories of Tra Vinh - Soc Trang provinces and 2 construction bidding packages for the construction of Ring Road 3 through Binh Duong province and Thu Duc City (Ho Chi Minh City),...

Perspective of Passenger Terminal T3 Project - Tan Son Nhat International Airport

Passenger terminal T3 at Tan Son Nhat airport, after completion, will be a domestic passenger terminal with a capacity of more than 20 million passengers/year, able to operate all types of Code C and Code E aircraft. The project also implemented simultaneously with connecting traffic routes invested by Ho Chi Minh City, to reduce traffic congestion around Tan Son Nhat airport. ACV has set a goal of completing the project before April 30, 2025 and putting it into operation.