At component project 1 of the Bien Hoa – Vung Tau expressway, dozens of officials, engineers, and workers are working throughout the Tet holiday.

Construction continued throughout the Lunar New Year holiday to get back to work immediately after the break.
On February 17th, representatives from the Dong Nai Provincial Investment and Construction Project Management Board announced that Construction Corporation No. 1 – JSC (CC1) is accelerating construction work throughout the Tet holiday on component project 1 of the Bien Hoa – Vung Tau expressway, determined to bring the project to completion ahead of schedule.
Mr. Bui Ngoc Lam – Director of Project CC1 – said: "To accelerate the progress and boost the construction momentum of Component Project 1 of the Bien Hoa – Vung Tau Expressway, we have planned to maintain operations throughout the Tet holiday. The construction site will operate continuously from the 27th day of the 12th lunar month until the end of the 7th day of the 1st lunar month (including peak days such as the 29th and 1st day of Tet)."

Regarding the technical plan, the contractor will simultaneously deploy three main construction fronts: Front 1: Focusing on completing the railings and thermal expansion joints in the Quan Thu Bridge area; Front 2: Constructing expansion joints, continuous thermal expansion joints, and median strips at Bridge 769; Front 3: Constructing the road section with foundation treatment, focusing on compacting the K98 topsoil layer and laying crushed stone aggregate.
Regarding management personnel, the CC1 Executive Board has deployed a 24/7 on-call team including: 1 Project Director, 1 Site Manager, and 2 Technical Officers to closely monitor the quality of the construction.
In terms of construction capacity, the contractor has mobilized 16 pieces of equipment and a permanent workforce of 22 to 25 people. All preparations have been completed to ensure smooth operation throughout the holiday period.
According to Mr. Lam, the unit's main goal is to proactively accelerate progress and exceed the plan. More importantly, maintaining the work pace throughout the Tet holiday aims to create positive momentum, helping the construction site immediately get back on track and return to normal construction after the holiday ends, avoiding sluggishness after Tet.
Showing care and concern for construction workers who work throughout the Tet holiday.
“Understanding the silent sacrifices of our engineers and workers who have to be away from their families, the Board of Directors and the Executive Board have implemented special policies to encourage and support them both materially and spiritually. We are committed to ensuring that all personnel remaining at the Component Project 1 construction site will both successfully complete their tasks and have a warm and fulfilling Tet holiday right at their workplace,” Mr. Lam further shared.

Earlier, on the afternoon of February 16th, leaders of the Dong Nai Provincial People's Committee visited, extended New Year greetings, and encouraged the staff, engineers, and workers who were working throughout the Tet holiday at the construction site of Component 1 of the Bien Hoa - Vung Tau Expressway. At the construction site, Chairman of the Provincial People's Committee Nguyen Van Ut acknowledged the responsible work ethic of the construction force during the Tet holiday, and emphasized the important significance of the Bien Hoa - Vung Tau Expressway Project in regional connectivity and promoting the province's socio-economic development.
Regarding the construction contractor, the Chairman of the Provincial People's Committee requested that they pay attention to the material and spiritual well-being of the workers, ensuring that they are allowed to work during the Tet holiday...

The Bien Hoa – Vung Tau Expressway project is a key infrastructure project with a total length of nearly 54 km, passing through Dong Nai province and Ho Chi Minh City. Of this, the section through Dong Nai province is over 34 km long, and the section through Ho Chi Minh City is over 19 km long.
Upon completion and commissioning, the project will contribute to reducing traffic congestion on National Highway 51, while also completing the transportation network in the southern region, creating more convenient connections between Dong Nai and Ho Chi Minh City. In particular, this expressway will also play a crucial role in effectively supporting the operation of Long Thanh Airport in the future.